School District of Clay County
Green Cove Springs, Florida
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway TIME: 7:00 p.m.
December 16, 2014 - Regular Meeting
Agenda Item #42


Item Title
C-44 Schematic/Preliminary/Final (Phase I, II & III) Plans and Specifications for Keystone Heights High School Lightning Protection System

Issue/Rationale

Each phase or combination of phases is submitted to the School Board for review and approval.  The plans have received staff review and are complete to Schematic/Preliminary/Final (Phase I, II & III) stage.

 



Recommended Action

Approve the Plans and Specifications.



Financial Impact

The Engineer’s construction cost estimate is $216,000.  The District budget for this project is $275,000.



Submitted By

John C. Merrill, Assistant Superintendent for Support Services